Friday, January 18, 2013

Substantial- Final Post

 
As we near Substantial Completion, the building is really coming together. Carpet is installed, the painting is complete and we are just working on a few punch list items. All of the trim work is completed and the hardware installed except a few items we are waiting to ship. The toilet partitions finally showed up yesterday and will be installed on Tuesday of next week. Plumbing, HVAC and electrical is complete except some labeling and a few punch list items that will be completed in the next couple of days. The folding partitions will be installed on Monday and Tuesday and the curtains next week also. The weather has warmed up a little the past couple of days which has made the Superintendent not as grouchy as normal.
 
 
 
 
 