Currently the foundation for the new addition is complete. We have completed 60% of the addition framing. All demo in the existing building is complete and new elements are currently being installed. The exterior of the project continues to progress as well with completions to storm drainage. The parking lot addition is currently going in and is about 30% complete. We are also prepare for the irrigation to begin on Monday 9-17-12. Below are our progress pics.
Digging Footers
Forming Stem Walls for Foundation
Building Slab Complete
Framing Begins
Front Elevation
Existing Slab Sawcut Lines
Existing Slab Demo to Accommodate New Plumbing
Existing Slab Patching
New Storage Building Foundation
We Found a Great Match for the Brick
New Retention Pond
New Roof Drains
Sept. 13 - 18