Weeks 4 to 6 August 15 - August 30 2012

Currently the foundation for the new addition is complete. We have completed 60% of the addition framing. All demo in the existing building is complete and new elements are currently being installed. The exterior of the project continues to progress as well with completions to storm drainage. The parking lot addition is currently going in and is about 30% complete. We are also prepare for the irrigation to begin on Monday 9-17-12. Below are our progress pics.

                                          Digging Footers


                                               Forming Stem Walls for Foundation


                                         Building Slab Complete


                                         Framing Begins








 







                                         Front Elevation


                                         Existing Slab Sawcut Lines


                                         Existing Slab Demo to Accommodate New Plumbing


                                         Existing Slab Patching


                                         New Storage Building Foundation


                                         We Found a Great Match for the Brick


                                         New Retention Pond


                                         New Roof Drains



                                          Sept. 13 - 18