The project is progressing nicely. We are 95% complete with the framing portion of the job scope. We are also 95% complete with the new Parking lot. The new water service is complete and the highway has been patched back per City of McCook requirements.The roofers will begin work tomorrow so stay tuned for the next update.
New Parking Lot
New Water Tap in Roadway
Framing Progress at Building Rear
Road Signage at Water Tap
Utility Trenching
Framing at New Entry Foyer
New Chapel/Cultural Center Framing
Framing at West Elevation
New Concrete Pavement
Lot Paving
It looks good! We've been wondering when the next update will becoming.