Currently the sprinkler system is being installed and sod will began being laid next week. It is expected that landscaping will be 90% complete by the end of the month. We've started the efface and will be starting the brick next Monday. Below are pictures from the last two weeks of work:
Approach & City Walk
Beam Installed at Grid Line 6
East Side of Building
Finishing New Approach
Fire Riser, Water Softener, Water Service
Folding Partition Header, Duct work in New Addition
Grading on West Side of Addition
Insulation, Gas Line and Rough in Electrical at Mech Mezz.
Landscaping East Side of Building
Main Sprinkler Line
Landscaping & Grading SE of Building
Rough in Duct work, Electrical Room 106
Rough in Electrical
SE Side of Building
Framing in New Multi Purpose Room
Sheet Rock Delivered
West Side of Building
Is it lame that I'm more excited about the water softener than anything else? lol
ReplyDelete