Tuesday, November 6, 2012

October 22- November 4, 2012


Landscaping is continuing with the sprinkler system installed on the West (front) side of the building and sod will be completed today on that side. Most of the planters are complete with fabric and rock in place. Mulch around the trees is currently being installed. The parking lot was striped this week and the wheel stops were installed. Storefronts are complete, EIFS is complete on the East side of the building and the brick has just started. It is expected that brick and EIFS will be completed in the next 2 weeks.
 
Cable has been pulled to the main panel and will have permanent power next week.  Fire suppression main lines are being installed, electrical is 90% roughed in and wires pulled, duct work is 60% installed and we will begin insulating and sheet rocking next week. The steeple is scheduled to be installed in 2 weeks.
 
East Side of Building

East Side of Building Parking Lot Striping

East Side of Building
 
West Side of Building Installing Sod
 
West Side of Building
 
North Side of Building
 
Store Front Installed

Main Fire Line & Duct Work Installed at Existing Building


Main Panel Set

Font Control Box
 
Utility Meter and CT Cabinet
 
Roof Drain Adapters Installed
 
Planters with Rocks
 
Sealants at Joints at New Parking Lot 

No comments:

Post a Comment