Landscaping is
continuing with the sprinkler system installed on the West (front) side of the
building and sod will be completed today on that side. Most of the
planters are complete with fabric and rock in place. Mulch around the trees is
currently being installed. The parking lot was striped this week and
the wheel stops were installed. Storefronts are complete, EIFS is
complete on the East side of the building and the brick has just started. It is expected that brick and EIFS will be completed in the next 2 weeks.
Cable has been pulled to the main panel and will have permanent power next
week. Fire suppression main lines are being installed, electrical is 90%
roughed in and wires pulled, duct work is 60% installed and we will begin insulating
and sheet rocking next week. The steeple is scheduled to be installed in
2 weeks.
East Side of Building
East Side of Building Parking Lot Striping
East Side of Building
West Side of Building Installing Sod
West Side of Building
North Side of Building
Store Front Installed
Main Fire Line & Duct Work Installed at Existing Building
Main Panel Set
Font Control Box
Utility Meter and CT Cabinet
Roof Drain Adapters Installed
Planters with Rocks
Sealants at Joints at New Parking Lot